Camp Projects List-April 2009
Projects remaining to complete for 2009
VOLUNTEER ITEMS (still needed this season)
- Repair edging on paddle boats
- Minor repairs to doors, screens, etc. est. < $ 50.00 and Labor
- Mow the water side of the dam
- Size and split firewood (14″) and move to a central location
- Replace doors on Cabin 6 est. < $200.00
- Plumb and repair door Cabin 5
- Remove Gutters from Pavilion
- Seal and repair elements of the Challenge Course est. < $200.00
- Replace Breakers and Outlets at Campground est. < $500.00 and Labor
- Seal holes into attic from outside of dormitory (1 or 2 small ones)
- Seal hole under dormitory at foundation
CONTRACTOR ITEMS (needed this season)
- Replace Compressor/Condenser Units on Cooler and Freezer .. est. $2,000.00
- Add on/off switch to kitchen exhaust unit . est. $200.00
- Repair steam table units ……. est. $400.00
- Replace thermostat on basement HVAC unit est. < $100.00
- Repair Heat Pump at Oaks est. < $300.00
- Gravel the camp road and parking lot…………. est. < $1,000.00
MAJOR PROJECTS
- Insulate and heat shower house for year round use est. $4,000.00
- Major repairs or replacement of camp truck est. $6,000.00
- Purchase a UTV (e.g. Mule® or Gator®) … est. $5,000.00
- Major repair and renovation of the pool est. $5,000.00 and Volunteer Labor
WATERFRONT:…………. est. $5,000.00
- Raise level of dam where it is lower
- Re-route and replace the dam overflow pipe
- Replace underground water supply pipes……. est. $10,000.00
- Purchase or Construct a Welcome Center est.$25,000.00 – $50,000.00
- Construct guest cabins with shower and toilet facilities… est. $150,000.00 each