COVENANT POINT CAMP AND RETREAT CENTER

MAINTENANCE NEED PROJECTIONS

 Click here for print friendly version.

  Camp Maintenance Needs-August 2009 (23.5 KiB, 113 hits)

CONTRACTOR  ITEMS

Harold G. Butzer

*4 Replace Compressor/Condenser and Evaporator Units on Freezer          est. $6,000.00

*7 Add on/off switch to kitchen exhaust unit          est. $200.00

*8 Repair steam table units          est. $400.00

Strickland & Sons Electric

*9 Install Dusk to Dawn Light at SW corner of Parking Lot          est. $1,000.00

All Plumbing Co.

*2 Replace (3) Water heaters in dining hall          $2,500.00

Cooney’s Hauling

*3 Gravel the camp road and parking lot         est. < $1,000.00

 

MAJOR PROJECTS

*1 Landscaping of play area (donation of some work possible)          est. $2,500.00

*10 Insulate and heat shower house for year round use         est. $4,000.00

*5 Replace camp riding mower         est. $6,000.00

*13 Major repairs to or replacement of camp truck         est. $6,000.00

*6 Major repair and renovation of the pool         est. $5,000.00 and Volunteer Labor

*12 Purchase a UTV (e.g. Mule® or Gator®)          est. $5,000.00

*11 WATERFRONT:         est. $5,000.00

- Raise level of dam where it is lower

- Re-route and replace the dam overflow pipe

*14 Replace underground water supply pipes         est. $10,000.00

*16 Purchase or Construct a Welcome Center         est.$25,000.00 – $50,000.00

*15 Construct guest cabins with shower and toilet facilities         est. $150,000.00 each